ASR water recharge project is not meeting expectations

As Wichita voters consider spending $250 million expanding a water project, we should look at the project’s history. So far, the ASR program has not performed near expectations, even after revising goals downward.

In November, Wichita voters will consider approval of a one cent per dollar sales tax. Of the $400 million expected to be collected over five years, $250 million is earmarked for a new water source. The city has decided that the new water supply will be implemented through expansion of the Aquifer Storage and Recovery program or ASR. This is a program whereby water is taken from the Little Arkansas River, treated, and injected in the Equus Beds aquifer. That water is then available in the future as part of the aquifer.

The city believes that ASR is a proven technology that will provide water and drought protection for many years and recommends that voters approve anywhere from $200 million to $250 million for its expansion.

According to city documents, the original capacity of the ASR phase II project to process water and pump it into the ground (the “recharge” process) was given as “Expected volume: 30 MGD for 120 days.” That translates to 3.6 billion gallons per year. ASR phase II was completed in 2011.

At a city council workshop in April 2014, Director of Public Works and Utilities Alan King briefed the council on the history of ASR, mentioning the original belief that ASR would recharge 11,000 acre feet of water per year. But he gave a new estimate for production, telling the council that “What we’re finding is, we’re thinking we’re going to actually get 5,800 acre feet. Somewhere close to half of the original estimates.” The new estimate translates to 1.9 billion gallons per year.

Based on this experience, the city has produced a revised estimate of ASR production capability. What has been the actual experience of ASR? The U.S. Geological Survey has ASR figures available here. I’ve gathered the data and performed an analysis.

Annual production

In 2012 ASR produced 37 million gallons of recharged water. In 2013 ASR recharged 366 million gallons, or 19 percent of the newly revised estimate of production capacity. In 2014 through September, ASR recharged 275 million gallons, or 14 percent of capacity. Extrapolating this nine months of production to a full year results in 367 million gallons produced for 2014, or 19 percent of capacity, the same value as in 2013. This may or may not be valid, but it gives an idea of how 2014 is proceeding.

So for the two most recent years, the ASR system has not operated near its designed capacity, even after revising that capacity downwards by half.

To place these production figures in context, the city uses 56 million gallons per day, on average. So the annual production of the ASR project is about 6.5 days of water usage.

Monthly production

Gallons of Water Recharged Through Recharge Basins and Wells during Wichita ASR phase 1 and phase 2, monthly. Click for larger version.

Gallons of Water Recharged Through Recharge Basins and Wells during Wichita ASR phase 1 and phase 2, monthly. Click for larger version.

The ASR system is able to draw water from the river only when the flow is above a certain level. The river is not above that level every day of the year, so we may want to take a look at how the ASR system performs for shorter periods of time. Here, we’ll use monthly data.

For a 30-day month, if the plant could be run at full design capacity each day, the production would be 900 million gallons. The best month ever for actual was 192 million gallons, with the second best at 120 million gallons.

If we take the 12 best months for production, including before ASR Phase II started operations, the amount of water recharged is 924 million gallons. That’s 49 percent of the revised expected annual production of 1.9 billion gallons.

If we take the 12 best months for production, after ASR Phase II started operations, the amount of water recharged is 673 million gallons. That’s 35 percent of revised expected annual production of 1.9 billion gallons.

The cumulative deficit

Gallons of Water Recharged Through Recharge Basins and Wells during Wichita ASR phase 2, cumulative. Click for larger version.

Gallons of Water Recharged Through Recharge Basins and Wells during Wichita ASR phase 2, cumulative. Click for larger version.

I’ve produced a chart of the cumulative production of the Wichita ASR project compared with the original projections and the lower revised projections. The lines for projections rise smoothly, although it is expected that actual production is not smooth. The second phase of ASR came online sometime in 2011, but no water was produced and recharged that year. So I started this chart with January 2012. Data is from U.S. Geological Survey.

The city and the “Yes Wichita” campaign say the ASR project is proven and is working. The available data, however, debunks this claim.

Featured image from Shutterstock

Bob Weeks

Bob Weeks is a blogger for liberty and economic freedom in Kansas: http://wichitaliberty.org. Find him onTwitter: @bob_weeks

More Posts - Website - Twitter - Facebook - YouTube

Categories: Environment, Policy, Waste, Fraud and Abuse

RELATED ARTICLES

  1. KS: Options for funding Wichita’s future water supply
  2. Wichita water rates seen as not encouraging conservation
  3. ASR water recharge project is not meeting expectations
  4. Wichita geologist sees water issues relating to the Equus Beds aquifer
  5. Wichita water projections remain fluid

COMMENTS

comments powered by Disqus
Login